General SummaryThis case is from a collection containing the full text of over 16,000 Supreme Court cases from 1793 to the present. The body of Supreme Court decisions are, effectively, the final interpretation of the Constitution. Only an amendment to the Constitution can permanently overturn an interpretation and this has happened only four times in American history.
Fleischer Engineering & Constr. Co. v. United States, 311 U.S. 15 (1940)
Please note: this case begins in mid-page. It therefore shares a citation with the last page of the previous case. If you are attempting to follow a link to the last page of 311 U.S. 7, click here.
Fleischer Engineering & Construction Co. v. United States, 311 U.S. 15 (1940) No. 15 Argued October 17, 18, 1940 Decided November 12, 1940 311 U.S. 15
CERTIORARI TO THE CIRCUIT COURT OF APPEALS
FOR THE SECOND CIRCUIT
Syllabus
1. The Miller Act of 1935, requiring contractors for public work of the United States to furnish a payment bond for the protection of persons supplying labor or materials, provides that a supplier having contractual relationship not with the contractor furnishing such bond, but with a subcontractor, "shall have a right of action upon the said payment bond upon giving written notice to said contractor. . . ." The Act further provides that "such notice shall be served by mailing the same by registered mail. . . ." Held, that a suit under the Act was maintainable although the notice was sent by ordinary mail, and not by registered mail, where it was otherwise sufficient and actually reached one of two joint and several contractors. P. 17.
2. With respect to the manner of giving the prescribed notice, the Act should be liberally construed in aid of its remedial purpose. P. 18.
107 F.2d 925 affirmed.
Certiorari, 309 U.S. 693, to review the affirmance of a judgment on a bond given by two contractors, with sureties, to secure payment for labor and material supplied for the performance of a contract with the United States.
Contents:
Chicago: U.S. Supreme Court, "Syllabus," Fleischer Engineering & Constr. Co. v. United States, 311 U.S. 15 (1940) in 311 U.S. 15 311 U.S. 16. Original Sources, accessed November 22, 2024, http://originalsources.com/Document.aspx?DocID=XIITWMUH88LBIUR.
MLA: U.S. Supreme Court. "Syllabus." Fleischer Engineering & Constr. Co. v. United States, 311 U.S. 15 (1940), in 311 U.S. 15, page 311 U.S. 16. Original Sources. 22 Nov. 2024. http://originalsources.com/Document.aspx?DocID=XIITWMUH88LBIUR.
Harvard: U.S. Supreme Court, 'Syllabus' in Fleischer Engineering & Constr. Co. v. United States, 311 U.S. 15 (1940). cited in 1940, 311 U.S. 15, pp.311 U.S. 16. Original Sources, retrieved 22 November 2024, from http://originalsources.com/Document.aspx?DocID=XIITWMUH88LBIUR.
|